Richmond NRP Contract 5

Richmond, Virginia

Morrison Engineers is in the process of installing 715 micropiles for the Richmond Wastewater Treatment Plant for English Construction. The piles have a maximum capacity of 180 KIPS in compression and 100 KIPS in tension.

These piles are being installed for the Sedimentation Facility at the existing treatment plant. This project will be fast pace and Morrison Engineers estimates duration of two weeks for the testing and nine weeks for installation.